Modular classroom demolition, secondary academy, North Essex

Demolition of a 320 m² steel-frame modular classroom block for a modular contractor, delivered inside the school holidays with full duty-of-care waste records. Read more.

Client
Modular building contractor (principal contractor)

Scope
Soft strip, mechanical demolition, foundation break-out and site clearance

Structure
Single-storey steel portal-frame modular block, approx. 320 m², on concrete pad foundations

Completed
June 2026

Demolition

Safe and efficient structural demolition services for projects of all sizes.

Soft Strip

Expert interior strip-outs to prepare your property for refurbishment.

Waste

Fast, affordable household and commercial waste removal. Environmently friendly.

Clearances

Professional site and property clearances, leaving your space clean and ready to use.

CASE STUDY

The academy was replacing an older modular classroom block with new accommodation. The modular contractor needed the existing block gone and the footprint cleared before their installation programme started, and all of it had to happen inside the school holidays so nothing overlapped with pupils on site.

An R&D asbestos survey came back clear before anything was touched. We soft stripped the block first, removing fixtures, services and internal finishes and segregating them at source. With the shell down to frame, the 14t excavator took the structure down in a controlled sequence, working away from the retained buildings with the exclusion zone held throughout. Foundations were broken out to the agreed scope and the site was cleared, graded and handed back level for the incoming works.

Waste left site on our own vehicles under carrier licence CBDU575260, split into metals, timber, inert and mixed streams with a transfer note for every load. The close-out pack included the RAMS, construction phase plan input, asbestos management plan, COSHH assessments, site records and a daily photo log.

Fixed window, delivered inside it. The modular installer started on time on a clean, level footprint. A client reference is available on request.

NEXT PACKAGE

Talk to us about your project

Tom Keenan, Director, 07949 496 448.
Ryan Lee, Commercial Director, 07771 525 124.
info@ewdsolutions.co.uk

Planning a demolition or strip-out package?

Call Now Button Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.