Demolition on a live, operational secure site, HMP Send, Surrey
In 2026 EWDS took down a redundant brick workshop and former changing room at HMP Send, and cleared the waste off a live, operational secure site. The buildings were taken down to slab level and the area was handed back clear. Read more.
Project type
Demolition on a live secure site
Location
HMP Send, Surrey
Scope
Demolition of a redundant brick workshop and former changing room, down to slab level, and removal of all waste
Completed
October 2026
Constraint
Live, operational secure site
Demolition
Safe and efficient structural demolition services for projects of all sizes.
Soft Strip
Expert interior strip-outs to prepare your property for refurbishment.
Waste
Fast, affordable household and commercial waste removal. Environmentally friendly.
Clearances
Professional site and property clearances, leaving your space clean and ready to use.
Redundant brick workshop and former changing room at HMP Send, still standing, before demolition.
Buildings removed at HMP Send and the slab handed back clear, with barriers left in place. A green cabinet outside the takedown remains in position.
CASE STUDY
The project
In 2026 EWDS was appointed to take down a redundant brick workshop and former changing room at HMP Send, and to clear the waste off site. The brief was to take the buildings down to slab level and hand the area back clear.
The prison stayed in use around the works. This was not an empty, closed site.
Challenges
Access, security and the method all had to fit a live operational regime. The buildings sat tight to the surrounding ground, and the waste had to leave the site as the demolition went on, rather than being stockpiled. Everyone on the team had to work to the site’s security rules for the whole of the job.
How the EWDS team delivered it
The plot was barriered off before work started. The structures were then taken down to slab level in a controlled sequence, and all arisings were removed from the site as the demolition progressed. The slab itself was left in place, and a green cabinet outside the takedown was left undisturbed.
The area was handed back clear, with barriers still in position around the slab.
Outcome
The redundant buildings were gone, the waste was off the live prison site, and the slab was handed back clear in October 2026.
NEXT PACKAGE
Talk to us about your project
EWDS Ltd is CHAS and PQS (SSIP) approved, with £5M public liability and £10M employers’ liability.
Tom Keenan, Director, 07949 496 448.
Ryan Lee, Commercial Director, 01375 309 432.
info@ewdsolutions.co.uk
On site
Demolition plot at HMP Send fenced and signed off, on a live operational secure site.