Most demolition delays happen before a machine arrives. Here is the order things need to happen in.
1. Surveys
An R&D asbestos survey is non-negotiable for demolition, and it needs to be done early enough that any licensed removal fits inside the programme rather than stopping it. A structural survey tells you what is holding what up, which decides whether the job is machine-led, hand-led or a mix.
2. Permissions
Demolition may need prior approval or full planning permission depending on the building, the site and whether it is in a conservation area. That sits with the client or their planning consultant, but it needs confirming before the programme is fixed.
3. Services
Gas, water, electricity and telecoms all need formal disconnection, with the paperwork to prove it. Lead times from the utilities are usually the longest single item in the pre-start programme, so these go in first.
4. CDM 2015
The Construction (Design and Management) Regulations 2015 apply to all construction work, demolition included. The client appoints duty holders, an F10 goes in on notifiable projects, and the arrangements for the demolition itself are recorded in writing before work starts.
5. Site set-up
Hoarding and exclusion zones, access and egress for plant and muckaway, dust suppression, protection for retained structures and neighbours, and a clear route for waste off site.
6. Method and sequence
The written sequence sets out what comes down, in what order, and what holds the rest up while it happens. Temporary works are agreed with your engineer where the scope needs it. We issue RAMS and the sequence for review before mobilisation.
What good preparation looks like on site
A controlled start, no stoppages waiting on utilities or surveys, waste segregated as it arises, and a site handed back clean and level for the next trade.